A428 Westbound ROAD CLOSURE

Posted: Wed, 27 Sep 2017 09:25 by Josie Flavell

CRICK CYCLEWAY WORKS A428 ROAD CLOSURE

Start Date: 25th September 2017

Completion Date: 17th November 2017

Due to the construction of a new cycleway from Junction 18 M1 Eldon Way industrial estate roundabout A428. Construction includes the installation of sheet piles to retain the new cycleway around the location of the culvert.

Traffic management will consist of lane narrowing and road closures to complete the scheme in full. The working times will be between 07:30 and 17:00 hours Monday to Friday, and there is the addition of weekend working if it is required.

Road Closure Dates are:

- A428; 25th September 2017 - 1 night 20:00 to 06:00

- Eldon Way Exit Only; 25th September 2017 - 2 weeks 07:30 to 17:00

- A428 Westbound - 9th October for 6 weeks (days) 07:30 to 17:00

The A428 westbound only closure is to ensure we keep the flow of traffic exiting the M1. A suitable diversion will be in place that will divert traffic via the A428 eastbound, through West Haddon and Watford and will join the A5 north back to Jct 19, M1.

If you have any queries please contact the Site Manager, Howard Grainger on 07740 394 416.

For more information please visit www.northamptonshire.gov.uk

Please report all defects and issues using Street Doctor via the above mentioned NCC website. Thank you.

Tags: News, Highways